Tanada wrote:The ridiculous thing is eastern nations don't have problems building units within contract time or at least fairly close to it.
Safety Problems Again Delay China’s Sanmen Westinghouse AP1000 Nuclear Energy ProjectNuclear energy proponents often cite the seeming ongoing support for nuclear energy in China and Russia when arguing that the western world is being left behind by its move away from the electricity generation modality. What they don’t tell you, though, is that the projects in question are in general running way behind schedule, and are repeatedly unnerving regulators due to the presence of unresolved “safety concerns.”
With that in mind, the China Daily has now reported that fuel-loading at the Sanmen nuclear energy project on the coast — to be the world’s first Westinghouse-designed AP1000 nuclear reactor — has again been delayed. This time due to the aforementioned “safety concerns.” Delays have been a common occurrence on the project, as the original plan was for the project to go online in 2014. Before moving on, it should be stated bluntly here that regulators in China haven’t approved any new nuclear energy projects in over two years. Clearly, the government there is beginning to become skeptical of the technology, and the timelines presented by project creators.
Elsewhere, the situation regarding nuclear energy project delays and cost-overruns is similar, with the technology seemingly not capable of supporting the grandiose claims often made by those hawking it to governments around the world.
CGN Power’s latest project delay deals another blow to China’s nuclear energy ambitionThe latest commissioning delay at CGN Power’s nuclear project in Taishan, in Guangdong province – the third in two years – will lead to a further deferral of 5 billion yuan (US$770 million) in annual revenues and potentially more cost overruns. The delay is another setback for China’s ambitious development programme.
The project was originally expected to come on line in 2015. The firm in early 2015 cited a “comprehensive evaluation” of the construction plan and risks for its first delay. In the second delay early last year, it said it needed to conduct “more experimental verifications in respect of its design and equipment”.
Korea delays completion of Shin Hanul-1-2 nuclear reactors